Project Updates – Wishart Townhouse 

📰 Project Details (Wishart Townhouse): 📰
Report Period: August 2016

Project: Parkside Wishart

Civil Construction Stage 2: Completed

Stage 1 Building Start Date: February 2016

Forecast Stage 1 Building Completion Date: November 2016

Forecast Stage 2 Building Start Date: 

June 2016

Forecast Stage 2 Building Completion Date: June 2017

Current Status:
New onsite display unit (unit 7) completed
Coora Street entry landscaping, footpath and fencing completed

First set of units (units 5-8) fully completed

Roofing completed

Driveways and roadways nearing completion

Electrical, Plumbing and Air Conditioning rough-ins are well underway

Kitchens, vanities and tiling all 50% complete

Internal painting underway

Fit off trades commenced

Civil works completed for Stage 2

Unit framing underway for Stage 2

Monthly Look Ahead:
Internal trades nearing completion
Courtyard and driveway landscaping underway

External cladding and brickwork completed

   
    
 

Author: johnsonhung

An Established Consulting Company in the Hear of Brisbane City - Position: Property & Investment & Business Consultant - Consulting Business Includes: Private Funds / Commercial Property & Investment / 188 & 132 Visa for Australia Major Immigration VISA / Project Funding / Home Construction & Design / Residential Property / House & Land / Apartment Projects.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.